How diversion of funds, illegal removal from office stalled Ibadan circular road project - Ladoja
A Former Governor of Oyo State, Senator Rashidi Ladoja has bemoaned how the diversion of funds by subsequent administrations to other projects, his illegal removal from office, failure of subsequent administrations to ask him as envisioner of the Ibadan circular road as reasons the project had failed to see the light of the day.
Ladoja who went historical about the idea of the circular road project said his administration commissioned the design for the project, paid compensation for the project, concessioned the project to two contractors and earmarked about N5billion to start the project but his illegal removal from office delayed commencement of the project.
He bemoaned that the project had also failed to see the light of the day because subsequent administrations after his, failed to consult him about his thinking behind the project.
Ladoja praised governor Seyi Makinde for reactivating the project, praying that the present administration accomplishes the project this time.
Ladoja said: “When I came in, the Baale of Ekotedo told me that there was already a plan for a circular road. I said that is a very good idea. I then asked Baale Ekotedo to prepare for me the viability of the project because it was his idea. When they brought it, we said we must make it work.
“We commissioned the design and in 2003/2004, we paid half a billion for the design. We paid compensation and by 2005, all was ready to start in 2006. We already earmarked about four or five billion to start the project. I knew this was a project spanning 110 kilometres but I said even if it takes more than 10 years, we should start the project. We concluded the design; we acquired the land and we paid compensation. The interruption we had in 2006 was what delayed the project because we will have started it in the first quarter of 2006.
“The first thing is to start the project, cross Ife road, cross Iwo road and end at Akinyele interchange. We said that if we toll it, and with the money collected from tolling, we will be able to do the other parts.
“We did contract that stretches to two contractors: KOPEK and CECCC, and we paid N1billion to each of them, in 2007, when I was returned to office.
“But, various people come to the government for various reasons. Part of it is that they don’t want to talk to those who preceded them. You cannot have everything in the file, however, good you are. And if the person is still alive, the minimum you can do is to ask the person’s thinking about a project. But instead of asking us what method we wanted to use, they simply said that it will cost about N35billion and that Oyo State cannot afford it.
“We are not asking them to do N110kilometres at a time. And the money was diverted. I was told it was the money that was used to do the Molete to Mokola dualisation and the Mokola to Agodi Gate dualisation. That is how that dream, at that time, ended and nobody talked about it until the next governor came.
“Governor Seyi Makinde exhumed the project and it was awarded again. But, I hope that this time around, we will get to the end of the project, by the grace of God.”